Mazoon targets a Q1 2027 start.
At Mazoon, there’s a big gap between the ore going into the plant and the product meant for sale. The $475 million project’s facility is designed to process 2.5 million tonnes of ore a year, while the target is about 115,000 tonnes of copper concentrate annually, at up to 21.5% copper. Construction is expected to finish in Q1 2027, with operations planned for the same quarter. CEO Matar bin Salem Al Badi said those expected volumes aren’t enough to justify a smelter in Oman, so the concentrate will be exported. If production grows, he said, a domestic smelter could be studied.