Energy and oil
Poland targets its first reactor by 2036
Poland’s target is to complete its first reactor by 2036. PEJ’s chief executive describes the timetable as ambitious and difficult but achievable, while warning that it leaves little room to maneuver and accounts for possible manufacturing or transport delays. Preparatory work is underway, and the companies are ordering components that take a long time to produce and deliver. PEJ needs to secure those items amid high demand at a limited number of factories able to make them, as competition for qualified workers also grows. The chief executive has said delays to early work could push the investment back several years.
2 publishers2 reports